Secondary containment, sized and proven

A dike that has not been calculated is a decoration. This is how capacity, freeboard and barrier selection are actually worked out, and what an inspector will ask you to show.

0Of the largest single vessel
0Of largest vessel for most state rules
024-hour design storm
0Plan review cycle
The rule in one paragraph

What sized containment means

40 CFR 112.8(c)(2) requires bulk storage containment to hold the capacity of the largest single container plus enough freeboard for precipitation. Industry practice, and most state programs, settle on 110% of the largest vessel.

Capacity

Largest single container, not the sum of all of them – plus displacement from every other tank and foundation inside the dike.

Freeboard

Enough additional depth for the 25-year, 24-hour storm at your location, unless the area is drained under an engineered procedure.

Demonstration

A written calculation in the plan. An inspector asks for the number and the basis, not a photograph of a wall.

Sizing tool

Work out your required capacity

Change any field and the numbers update. Nothing is sent anywhere - the maths runs in your browser.

Secondary containment sizing

SPCC sizing for a single-tank containment area — 110% of the largest vessel plus rainfall freeboard.

Required capacity (110%)—
Rainfall allowance—
Net available capacity—
Minimum wall height—

Planning aid only. 40 CFR 112 requires a sized, engineered design; most SPCC plans must be certified by a licensed P.E.

Barrier selection

What to line it with

Permeability is only half the question. The other half is what happens at the joints, in the cold, and under a truck.

BarrierSeamsElongationCold limitDrive-overRepairable in place
Spray polyureaNone300-600%-60°F✓✓
Reinforced PVC linerHeat-welded200-350%10°F✗✓
HDPE geomembraneFusion-welded500-700%-40°F✗✓
Concrete, sealedControl jointsNegligible-40°F✓✗
Compacted clayNoneNegligibleVaries✓✗

Typical values for containment-grade systems. Confirm against the manufacturer data sheet for your specific product.


Field practice

The five failures we keep investigating

  1. Nobody deducted displacement

    Every additional tank, pump skid and foundation inside the dike takes volume away from the containment. On congested pads this routinely costs 10-15% of nominal capacity.

  2. The drain valve was left open

    A containment area with an open gravity outfall is not containment. Valves stay locked closed and are opened only under a written, logged procedure after inspection of the water.

  3. The coating was sprayed below dew point

    Condensation on the substrate is invisible and fatal to adhesion. Substrate temperature must be at least 5°F above the dew point through the whole application window.

  4. Penetrations were never detailed

    Pipe penetrations, conduit and anchor bolts are where liners leak. Each one needs a detail, and each one needs to be on the inspection route.

  5. The wall was never re-checked after a tank change

    Swapping in a bigger tank changes the required capacity. The plan is amended within six months of any change that materially affects discharge potential.

Inspection

Monthly walk-around checklist

Tick these off as you go. Your progress is remembered in this browser.

Secondary containment inspection

0/10
Questions

Frequently asked

Is it 100% or 110% of the largest tank?

The federal rule says the capacity of the largest single container plus sufficient freeboard for precipitation. It does not name a percentage. 110% is the convention that satisfies that wording in most climates, and several state programs require it outright. In a high-rainfall region 110% may still be short – run the storm number.

Do I count every tank in the dike?

For required capacity, no – only the largest single container. For available capacity, yes: every other tank and foundation displaces volume you would otherwise have.

Can I use a liner under gravel?

Yes, and it is common for transformer and fire-rated containment. Specify a cushion geotextile above and below the liner, and accept that inspection becomes indirect – you are relying on the outfall sample rather than a visual check.

How often must containment be inspected?

The rule requires inspections on a written schedule with records kept for three years. Monthly visual inspection plus an annual documented condition assessment is what most member facilities run.

Does a self-certified Tier I plan still need sized containment?

Yes. Tier I changes who signs the plan, not what the plan requires. Any deviation from the standard containment requirements needs a P.E.