A dike that has not been calculated is a decoration. This is how capacity, freeboard and barrier selection are actually worked out, and what an inspector will ask you to show.
40 CFR 112.8(c)(2) requires bulk storage containment to hold the capacity of the largest single container plus enough freeboard for precipitation. Industry practice, and most state programs, settle on 110% of the largest vessel.
Largest single container, not the sum of all of them – plus displacement from every other tank and foundation inside the dike.
Enough additional depth for the 25-year, 24-hour storm at your location, unless the area is drained under an engineered procedure.
A written calculation in the plan. An inspector asks for the number and the basis, not a photograph of a wall.
Change any field and the numbers update. Nothing is sent anywhere - the maths runs in your browser.
SPCC sizing for a single-tank containment area — 110% of the largest vessel plus rainfall freeboard.
Planning aid only. 40 CFR 112 requires a sized, engineered design; most SPCC plans must be certified by a licensed P.E.
Permeability is only half the question. The other half is what happens at the joints, in the cold, and under a truck.
| Barrier | Seams | Elongation | Cold limit | Drive-over | Repairable in place |
|---|---|---|---|---|---|
| Spray polyurea | None | 300-600% | -60°F | ✓ | ✓ |
| Reinforced PVC liner | Heat-welded | 200-350% | 10°F | ✗ | ✓ |
| HDPE geomembrane | Fusion-welded | 500-700% | -40°F | ✗ | ✓ |
| Concrete, sealed | Control joints | Negligible | -40°F | ✓ | ✗ |
| Compacted clay | None | Negligible | Varies | ✓ | ✗ |
Typical values for containment-grade systems. Confirm against the manufacturer data sheet for your specific product.
Every additional tank, pump skid and foundation inside the dike takes volume away from the containment. On congested pads this routinely costs 10-15% of nominal capacity.
A containment area with an open gravity outfall is not containment. Valves stay locked closed and are opened only under a written, logged procedure after inspection of the water.
Condensation on the substrate is invisible and fatal to adhesion. Substrate temperature must be at least 5°F above the dew point through the whole application window.
Pipe penetrations, conduit and anchor bolts are where liners leak. Each one needs a detail, and each one needs to be on the inspection route.
Swapping in a bigger tank changes the required capacity. The plan is amended within six months of any change that materially affects discharge potential.
Tick these off as you go. Your progress is remembered in this browser.
The federal rule says the capacity of the largest single container plus sufficient freeboard for precipitation. It does not name a percentage. 110% is the convention that satisfies that wording in most climates, and several state programs require it outright. In a high-rainfall region 110% may still be short – run the storm number.
For required capacity, no – only the largest single container. For available capacity, yes: every other tank and foundation displaces volume you would otherwise have.
Yes, and it is common for transformer and fire-rated containment. Specify a cushion geotextile above and below the liner, and accept that inspection becomes indirect – you are relying on the outfall sample rather than a visual check.
The rule requires inspections on a written schedule with records kept for three years. Monthly visual inspection plus an annual documented condition assessment is what most member facilities run.
Yes. Tier I changes who signs the plan, not what the plan requires. Any deviation from the standard containment requirements needs a P.E.
Members can submit a tank schedule and site plan for a no-cost technical review. We will tell you whether the calculation holds up before an inspector does.